Nutbrook Group worked closely with TasWater to carry out audits of 3 data centres with a view to improving operational and service level efficiencies. The result of the project will be to provide a long-term strategic approach to the on-going management of their assets through the various lifecycles.

A key focus on this project was to identify data centre capacity issues/choke points and associated risks to reduce the TasWater risk profile. Other services included a review of maintenance schedules, and determining site criticality to develop a minimum infrastructure requirement for Fixed Plant and Equipment (FP&E).

 

 

In addition to this, Nutbrook Group assisted TasWater in determining site criticality and develop a minimum infrastructure requirement for Fixed Plant and Equipment (FP&E).

 

– Provide standards for key categories of our points of presence

– Water Treatment plant (Large / Small)

– Sewage Treatment plant (Large / Small)

– Pumping station

– Depots